Seed Access Road: the 21 km spine from Dondapadu to Undavalli
This is the road that makes Amaravati twenty minutes from Vijayawada. Two of its three phases are built or under way; the third, with its cable bridge to Kanakadurga Varadhi, starts at the end of August 2026.
Last reviewed 2026-08-27
- 21.77 km
- Total length
- 18.3 km
- Phase 1 complete
- ₹593 cr
- Phase 3 (3.5 km + bridge)
- 29 Aug 2026
- Phase 3 works begin
The three phases
| Phase | Stretch | Status |
|---|---|---|
| Phase 1 | 18.3 km, Dondapadu to Venkatapalem | Completed by 2018 (APCRDA, about ₹1,519 crore for the road overall). |
| Phase 2 | Venkatapalem to Undavalli | Works began September 2025 after years of delay; land notification of 12.58 acres across Undavalli (10.5), Penumaka (0.65), Mandadam (0.7) and Rayapudi (0.72) issued January 2026; High Court dismissed challenges to the acquisition in 2026. |
| Phase 3 | 3.5 km from Prakasam Barrage side to Manipal Hospital, with a 320 m cable-stayed bridge joining NH-16 at Kanakadurga Varadhi | ₹593.03 crore; tenders opened 27 August 2026; works from 29 August 2026. |
Why it matters
The E3 is the capital's main access from Vijayawada and carries the planned BRTS, cycle tracks, sidewalks, green belts and utility ducts. The Chief Minister formally launched the corridor on 13 August 2026. Every village it passes, from Dondapadu through Venkatapalem to Undavalli, becomes a frontage village, and every plot within a few minutes of it reads differently in a listing.
Questions people ask
Is the Seed Access Road open?
The first 18.3 km from Dondapadu to Venkatapalem has been in use since 2018. The Venkatapalem to Undavalli stretch has been under construction since September 2025, and the bridge link to NH-16 starts on 29 August 2026.