Government housing in Amaravati: the towers for legislators, officers and employees

The half-finished towers you see from the Seed Access Road are these. They were the most visible victims of the 2019 pause, and they are among the first buildings now being finished.

Last reviewed

Government employee and legislator residential tower groups
Housing · Illustration based on APCRDA’s photographs, not a live progress image. APCRDA published reference

What is being built

MLA quartersMLC quartersOfficers (AIS)About 420 units in the first phase, handed over from July 2026.
HousingScaleMoney and date
Flats for gazetted and class-4 officers1,440 flats₹594.54 crore, sanctioned 3 Dec 2024
Flats for non-gazetted officers1,140 flats₹607.50 crore, sanctioned 3 Dec 2024
Bungalows for All India Service officers115 bungalows₹516.6 crore, plus ₹226.26 crore for quarters infrastructure
MLA, MLC and AIS residential towersMultiple towersAPCRDA's completion target: October 2026
Ministers, judges and senior officers194 bungalows over 0.96 mn sq ft (2017 plan)₹760 crore in the 2017 estimate
Happy Nest (APCRDA's public housing project)Restarted 2024Revised at ₹984.10 crore

Why it matters to everyone else

When several thousand government families live in the capital instead of driving in from Vijayawada and Guntur, the interim complex starts to become a town. Schools, clinics, shops and demand for rented homes follow. The projects launched on 2 May 2025 included housing for 5,200 families.

Questions people ask

When will the Amaravati MLA quarters be ready?

APCRDA set October 2026 as the completion target for the MLA, MLC and AIS officer residential towers. Look for an official handover notice before you treat them as finished.