Housing

Government housing: the towers for legislators, officers and employees

The half-finished towers you see from the Seed Access Road are these. They were the most visible casualty of the 2019 pause and are among the first things being completed.

Last reviewed 2026-08-27

What is being built

MLA quartersMLC quartersOfficers (AIS)About 420 units in the first phase, handed over from July 2026.
HousingScaleMoney and date
Flats for gazetted and class-4 officers1,440 flats₹594.54 crore, sanctioned 3 Dec 2024
Flats for non-gazetted officers1,140 flats₹607.50 crore, sanctioned 3 Dec 2024
Bungalows for All India Service officers115 bungalows₹516.6 crore, plus ₹226.26 crore quarters infrastructure
MLA, MLC and AIS residential towersMultiple towersAPCRDA targets completion by October 2026
Ministers, judges and senior officers194 bungalows over 0.96 mn sq ft (2017 plan)₹760 crore in the 2017 estimate
Happy Nest (APCRDA's public housing project)Restarted 2024Revised at ₹984.10 crore

Why it matters beyond the residents

Several thousand government families living in the capital, rather than commuting from Vijayawada and Guntur, is what turns the interim complex into a town: schools, clinics, shops and rental demand follow. The 2 May 2025 relaunch included housing for 5,200 families in the projects launched that day.

Questions people ask

When will the Amaravati MLA quarters be ready?

APCRDA has targeted the MLA, MLC and AIS officer residential towers for completion by October 2026.