Amaravati development progress: the latest verified milestones
A dated summary of what is happening in the capital. Each topic links to its evidence and its own page. We label each one as working, under construction or out to tender, so you can tell them apart.
Last reviewed

The overall numbers
A review reported on 13 September 2026 listed 119 major capital projects worth ₹66,802 crore. Of these, 113 were approved, 97 had started and 4 were complete. ₹58,093 crore of work was under way, ₹12,731 crore had been spent since 2024, and ₹41,188 crore of loans had been arranged from the World Bank, HUDCO, NABARD, NABFID and the state power finance corporation.
In April 2026 the figure under review was ₹57,821 crore, so the two numbers are close. The Chief Minister used a rounder figure of about ₹50,000 crore in a speech on 23 September. Different counts include different projects, so go by the dated, itemised figure.
Progress at a glance
| Topic | Stage | Latest evidence |
|---|---|---|
| ORR tenders | Tendering | NHAI published four construction packages on 2 October 2026. Bids are due on 18 November. |
| Railway line | Tendering | Package 4, Vaddamanu to Nambur, went to tender on 4 October 2026. |
| Seed Access Road | Phase 2 open | The 3.92 km second phase opened on 13 August 2026. Phase 3 was announced for 29 August. |
| Secretariat towers | Under construction | Facade work on the GAD and HOD towers reviewed on 22 September 2026. |
| Assembly | Under construction | ₹661 crore approved for the 250 m spire on 18 September 2026, with permission to tender. |
| Quantum Valley | Building nearly done | The Chief Minister said the quantum computer starts work on 3 February 2027. |
| TTD temple | Expansion under construction | Official inspection of the prakaram and gopuram works in August. |
| Hotels | Different stages | Foundation ceremonies, agreements and planning entries, each tracked separately. |
| Education | Working campuses and new projects | VIT-AP, SRM-AP, Amrita and NID are running, alongside institutions still being built. |
| AIIMS Mangalagiri | Operational | 970 beds after a burns and plastic surgery block opened in August 2026. |
| New institutions | Land and foundation stones | LV Prasad Eye Institute foundation stone at Abbarajupalem (23 Sep), LIC office land at Uddandarayunipalem (11 Sep), NIELIT quantum and AI university (8.5 acres). |
| Cricket stadium | Working for cricket | Official APL records confirm matches at Mangalagiri. |
| Land pooling | Ongoing | Pedamadduru at 75% in September; Mothadaka notified for a new round in August. |
Tenders for the government complex
APCRDA's notices include a district cooling tender started on 28 August 2026 and a call for third-party construction quality checks started on 24 September 2026. When we checked on 2 October, the listing gave 3 October as the closing date for both. These are tenders, not certificates that the buildings are finished.
How to read a project update
Every milestone covers a set scope. A tender is about the package named in the notice. A foundation ceremony marks a start. A working service shows the thing is in use. A completion date stays a target until the responsible authority reports that the work is done. Follow the news log for dated entries and the infrastructure board for each project.
Want a straight answer about a plot or a village?
We live and work in the capital villages. Send the survey number or LP number and we will tell you what we know, including the things that should make you pause.