Amaravati infrastructure: one status board for every major project

Thirteen projects, each with a page that says what is built, what is tendered and what is only proposed. We update the board when a dated source changes.

Last reviewed 2026-08-27

₹57,821 cr
Works in progress (Apr 2026)
Apr 2027
Trunk roads target
2027
High Court complex target
2028
Assembly target

Status board

ProjectStatusWhere it standsNext
Seed Access Road (E3)under construction21.77 km Dondapadu to Undavalli; phase 1 (18.3 km) donePhase 3 works from 29 Aug 2026; tenders opened 27 Aug
Trunk roads (E and N grid)under construction₹4,313.78 crore of road and utility packagesCompletion target April 2027
Inner Ring RoadtenderingTo be built under PPPPrivate partner selection; land from Phase 2 villages
Outer Ring Roadland acquisition189 km, 6-lane NHAI expressway, about ₹16,000 croreSurveys and notifications across districts
Secretariat and HoD towersunder constructionFive towers on 32 acres; ₹4,668 crore tendersMinisters target one tower a month at completion stage
High Court complexunder construction2B+G+7, about 45,000 tonnes of steelTargeted 2027; design consultancy revised Aug 2026
Legislative Assemblyunder construction250 m conical tower; L&T, ₹617 croreTargeted 2028
Government housingunder constructionMLA, MLC and AIS residential towersAPCRDA target October 2026
Errupalem–Amaravati–Nambur railland acquisition57 km, ₹2,047 to 2,245 crore, Krishna bridge 3.2 kmAbout 300 acres being acquired in NTR district
Vijayawada Metro phase 1tendering38.4 km, ₹11,009 crore, approved Dec 2024Civil bids of ₹4,150 crore invited July 2025
International airportplanningReported at Ravela, Tadikonda; 4,618 acresFeasibility (TEFR) commissioned; final decision pending
Sports Cityland acquisitionAbout 2,500 acres from Phase 2 landWork promised within a year of Dec 2025
Kondaveeti Vagu and Pala Vagu worksunder construction₹1,585.95 crore reservoirs and channelsObstruction removal between Rayapudi and Venkatapalem (Jun 2026)

Project pages

tenderingInner Ring RoadTo be built under PPP. Next: Private partner selection; land from Phase 2 villages.Read moreland acquisitionOuter Ring Road189 km, 6-lane NHAI expressway, about ₹16,000 crore. Next: Surveys and notifications across districts.Read moreunder constructionSeed Access Road (E3)21.77 km Dondapadu to Undavalli; phase 1 (18.3 km) done. Next: Phase 3 works from 29 Aug 2026; tenders opened 27 Aug.Read moreunder constructionTrunk roads (E and N grid)₹4,313.78 crore of road and utility packages. Next: Completion target April 2027.Read moreunder constructionSecretariat and HoD towersFive towers on 32 acres; ₹4,668 crore tenders. Next: Ministers target one tower a month at completion stage.Read moreunder constructionHigh Court complex2B+G+7, about 45,000 tonnes of steel. Next: Targeted 2027; design consultancy revised Aug 2026.Read moreunder constructionLegislative Assembly250 m conical tower; L&T, ₹617 crore. Next: Targeted 2028.Read moreland acquisitionErrupalem–Amaravati–Nambur rail57 km, ₹2,047 to 2,245 crore, Krishna bridge 3.2 km. Next: About 300 acres being acquired in NTR district.Read moreplanningInternational airportReported at Ravela, Tadikonda; 4,618 acres. Next: Feasibility (TEFR) commissioned; final decision pending.Read moretenderingVijayawada Metro phase 138.4 km, ₹11,009 crore, approved Dec 2024. Next: Civil bids of ₹4,150 crore invited July 2025.Read moreland acquisitionSports CityAbout 2,500 acres from Phase 2 land. Next: Work promised within a year of Dec 2025.Read moreunder constructionKondaveeti Vagu and Pala Vagu works₹1,585.95 crore reservoirs and channels. Next: Obstruction removal between Rayapudi and Venkatapalem (Jun 2026).Read moreunder constructionGovernment housingMLA, MLC and AIS residential towers. Next: APCRDA target October 2026.Read moreConnectivityAmaravati Connectivity: Roads and DistancesHow Amaravati connects today and tomorrow: NH-16 and Kanakadurga Varadhi, the Vijayawada road, distances to Vijayawada, Guntur and the airport.Read more

How to read the board

Being builtSeed Access RoadTrunk roadsSecretariat towersHigh CourtAssemblyFlood worksLand being takenRailway lineOuter Ring RoadStill on paperAirportInner Ring RoadMetro to Amaravati

"Operational" means open to use. "Under construction" means a contractor is on site. "Tendering" means bids are invited or being evaluated. "Land acquisition" means the alignment is approved and land is being taken. "Planning" means studies and approvals are still in progress; the airport is the clearest example. Where reports disagree on a number, the project page shows both with dates.

Questions people ask

Which Amaravati projects are actually under construction in 2026?

The Seed Access Road (phase 2 and 3), trunk roads, the five Secretariat towers, the High Court complex, the Assembly building, government housing towers and the Kondaveeti Vagu flood works. The railway line and Outer Ring Road are in land acquisition; the airport is at feasibility stage.