Amaravati infrastructure: where every major project stands

One board for the big projects. Each one has its own page that says what is built, what is out to tender and what is still only a proposal. We change the board when a dated source changes.

Last reviewed

A road strip, water pipe, electric pylon and rail wheel arranged around an abstract central connection node
Illustration · Explanatory symbols, not an official plan, record or site photograph.
₹58,093 cr
Works under way (Sep 2026)
Mar 2027
Trunk roads target (Jul 2026)
2027
High Court complex target
2028
Assembly target

Status board

ProjectStatusWhere it standsNext
AIIMS MangalagirioperationalHospital and medical college working; 970 beds since Aug 2026Check the institute's own clinic and admission notices
Mangalagiri cricket stadiumoperationalACA ground that hosted APL 2026 matchesWatch ACA notices for fixtures and new facilities
Seed Access Road (E3)under construction21.77 km Dondapadu to Undavalli; phases 1 and 2 openPhase 3 to NH-16 announced for 29 Aug 2026; start not yet confirmed
Trunk roads (E and N grid)under construction₹4,313.78 crore of road and utility packagesMinister's target March 2027 (earlier April 2027)
Inner Ring RoadtenderingTo be built under PPPNo private partner yet; pooling for its land began in Mothadaka, Kantheru and Tadikonda
Outer Ring RoadtenderingSix-lane ring of about 195 km; NHAI invited bids on 2 Oct 2026Bids due 18 Nov 2026; no contractor chosen yet
Secretariat and HoD towersunder constructionFive towers on 32 acres; ₹4,668 crore tendersFacade work under way (Sep 2026); two-year target for the main buildings
High Court complexunder construction2B+G+7, about 45,000 tonnes of steelTarget 2027; design consultancy revised Aug 2026
Legislative Assemblyunder construction250 m conical tower; L&T, ₹617 crore₹661 crore spire approved for tender (Sep 2026); target 2028
Government housingunder constructionMLA, MLC and AIS residential towersAPCRDA's completion target was October 2026
Errupalem–Amaravati–Nambur railtendering57 km, ₹2,047 to 2,245 crore, Krishna bridge 3.2 kmPackage 4 tendered 4 Oct 2026; land acquisition in NTR district
Vijayawada Metro phase 1tendering38.4 km, ₹11,009 crore, approved Dec 2024Civil bids of ₹4,150 crore invited July 2025
International airportplanningPlanned near Ravela, Tadikonda; 4,618 acres in the studyFeasibility report done; Cabinet decision awaited
Sports CityplanningAbout 2,500 acres of Phase 2 land proposedListed at pre-DPR stage in the government PPP pipeline
Kondaveeti Vagu and Pala Vagu worksunder construction₹1,585.95 crore reservoirs and channelsPala Vagu obstruction removal, Rayapudi to Venkatapalem (Jun 2026)

Project pages

tenderingInner Ring RoadTo be built under PPP. Next: No private partner yet; pooling for its land began in Mothadaka, Kantheru and Tadikonda.Read moretenderingOuter Ring RoadSix-lane ring of about 195 km; NHAI invited bids on 2 Oct 2026. Next: Bids due 18 Nov 2026; no contractor chosen yet.Read moreunder constructionSeed Access Road (E3)21.77 km Dondapadu to Undavalli; phases 1 and 2 open. Next: Phase 3 to NH-16 announced for 29 Aug 2026; start not yet confirmed.Read moreunder constructionTrunk roads (E and N grid)₹4,313.78 crore of road and utility packages. Next: Minister's target March 2027 (earlier April 2027).Read moreunder constructionSecretariat and HoD towersFive towers on 32 acres; ₹4,668 crore tenders. Next: Facade work under way (Sep 2026); two-year target for the main buildings.Read moreunder constructionHigh Court complex2B+G+7, about 45,000 tonnes of steel. Next: Target 2027; design consultancy revised Aug 2026.Read moreunder constructionLegislative Assembly250 m conical tower; L&T, ₹617 crore. Next: ₹661 crore spire approved for tender (Sep 2026); target 2028.Read moretenderingErrupalem–Amaravati–Nambur rail57 km, ₹2,047 to 2,245 crore, Krishna bridge 3.2 km. Next: Package 4 tendered 4 Oct 2026; land acquisition in NTR district.Read moreplanningInternational airportPlanned near Ravela, Tadikonda; 4,618 acres in the study. Next: Feasibility report done; Cabinet decision awaited.Read moretenderingVijayawada Metro phase 138.4 km, ₹11,009 crore, approved Dec 2024. Next: Civil bids of ₹4,150 crore invited July 2025.Read moreplanningSports CityAbout 2,500 acres of Phase 2 land proposed. Next: Listed at pre-DPR stage in the government PPP pipeline.Read moreunder constructionKondaveeti Vagu and Pala Vagu works₹1,585.95 crore reservoirs and channels. Next: Pala Vagu obstruction removal, Rayapudi to Venkatapalem (Jun 2026).Read moreunder constructionGovernment housingMLA, MLC and AIS residential towers. Next: APCRDA's completion target was October 2026.Read moreConnectivityAmaravati Connectivity: Roads and DistancesHow to reach Amaravati today and later: NH-16 and the Kanakadurga Varadhi, the Vijayawada road, and road distances to Vijayawada, Guntur and the airport.Read moreDevelopment update · October 2026Amaravati ORR Tenders: NHAI Notice, Oct 2026Amaravati ORR tenders published by NHAI on 2 October 2026: the four packages, their tender IDs, route sections and the November bid dates on the portal.Read moreoperationalAIIMS MangalagiriHospital and medical college working; 970 beds since Aug 2026. Next: Check the institute's own clinic and admission notices.Read moreoperationalMangalagiri cricket stadiumACA ground that hosted APL 2026 matches. Next: Watch ACA notices for fixtures and new facilities.Read more

How to read the board

Being builtSeed Access RoadTrunk roadsSecretariat towersHigh CourtAssemblyFlood worksLand being takenRailway lineOuter Ring RoadStill on paperAirportInner Ring RoadMetro to Amaravati

"Operational" means you can use it today. "Under construction" means a contractor is working on site. "Tendering" means bids have been invited or are being evaluated. "Land acquisition" means the route is approved and land is being taken. "Planning" means studies and approvals are still going on; the airport is the clearest example. When two reports give different numbers, the project page shows both, with their dates.

Questions people ask

Which Amaravati projects are actually under construction in 2026?

The Seed Access Road (each phase is at a different stage), the trunk roads, the five Secretariat towers, the High Court complex, the Assembly building, the government housing towers and the Kondaveeti Vagu drainage works. The railway line and the Outer Ring Road are at the tender stage, with land acquisition still going on for both. The airport is waiting for a Cabinet decision.

Want a straight answer about a plot or a village?

We live and work in the capital villages. Send the survey number or LP number and we will tell you what we know, including the things that should make you pause.