Amaravati infrastructure: where every major project stands
One board for the big projects. Each one has its own page that says what is built, what is out to tender and what is still only a proposal. We change the board when a dated source changes.
Last reviewed

- ₹58,093 cr
- Works under way (Sep 2026)
- Mar 2027
- Trunk roads target (Jul 2026)
- 2027
- High Court complex target
- 2028
- Assembly target
Status board
| Project | Status | Where it stands | Next |
|---|---|---|---|
| AIIMS Mangalagiri | operational | Hospital and medical college working; 970 beds since Aug 2026 | Check the institute's own clinic and admission notices |
| Mangalagiri cricket stadium | operational | ACA ground that hosted APL 2026 matches | Watch ACA notices for fixtures and new facilities |
| Seed Access Road (E3) | under construction | 21.77 km Dondapadu to Undavalli; phases 1 and 2 open | Phase 3 to NH-16 announced for 29 Aug 2026; start not yet confirmed |
| Trunk roads (E and N grid) | under construction | ₹4,313.78 crore of road and utility packages | Minister's target March 2027 (earlier April 2027) |
| Inner Ring Road | tendering | To be built under PPP | No private partner yet; pooling for its land began in Mothadaka, Kantheru and Tadikonda |
| Outer Ring Road | tendering | Six-lane ring of about 195 km; NHAI invited bids on 2 Oct 2026 | Bids due 18 Nov 2026; no contractor chosen yet |
| Secretariat and HoD towers | under construction | Five towers on 32 acres; ₹4,668 crore tenders | Facade work under way (Sep 2026); two-year target for the main buildings |
| High Court complex | under construction | 2B+G+7, about 45,000 tonnes of steel | Target 2027; design consultancy revised Aug 2026 |
| Legislative Assembly | under construction | 250 m conical tower; L&T, ₹617 crore | ₹661 crore spire approved for tender (Sep 2026); target 2028 |
| Government housing | under construction | MLA, MLC and AIS residential towers | APCRDA's completion target was October 2026 |
| Errupalem–Amaravati–Nambur rail | tendering | 57 km, ₹2,047 to 2,245 crore, Krishna bridge 3.2 km | Package 4 tendered 4 Oct 2026; land acquisition in NTR district |
| Vijayawada Metro phase 1 | tendering | 38.4 km, ₹11,009 crore, approved Dec 2024 | Civil bids of ₹4,150 crore invited July 2025 |
| International airport | planning | Planned near Ravela, Tadikonda; 4,618 acres in the study | Feasibility report done; Cabinet decision awaited |
| Sports City | planning | About 2,500 acres of Phase 2 land proposed | Listed at pre-DPR stage in the government PPP pipeline |
| Kondaveeti Vagu and Pala Vagu works | under construction | ₹1,585.95 crore reservoirs and channels | Pala Vagu obstruction removal, Rayapudi to Venkatapalem (Jun 2026) |
Project pages
How to read the board
"Operational" means you can use it today. "Under construction" means a contractor is working on site. "Tendering" means bids have been invited or are being evaluated. "Land acquisition" means the route is approved and land is being taken. "Planning" means studies and approvals are still going on; the airport is the clearest example. When two reports give different numbers, the project page shows both, with their dates.
Questions people ask
Which Amaravati projects are actually under construction in 2026?
The Seed Access Road (each phase is at a different stage), the trunk roads, the five Secretariat towers, the High Court complex, the Assembly building, the government housing towers and the Kondaveeti Vagu drainage works. The railway line and the Outer Ring Road are at the tender stage, with land acquisition still going on for both. The airport is waiting for a Cabinet decision.